Mesquite ISD 2019 Bond Project | Additions to Cannaday ES & A.C. New MS

In Progress K-12 | Dallas

  • Project Scope 36,750 SF Additions & Renovations to Cannaday ES & A.C. New MS
  • Completion Date July 2021
  • Owner Mesquite ISD
  • Architect WRA Architects

Cannaday Elementary School – Classroom Addition

The project includes a new one-story classroom addition (15,000 SF) to the existing Cannaday Elementary School, adding 11 additional classrooms. 

The scope of construction also includes an ICC500 storm shelter of approximately 7,500 SF within the classroom addition. The storm shelter will have an occupant capacity for the entire school.

The project’s site development includes revising existing site utilities in the new building and additional parking area.

A.C. New Middle School – Phase 2 Addition

The project includes a new one-story second gym addition (12,750 SF) and a one-story classroom addition (9,000 SF) to the existing A.C. New Middle School. 

Project Scope Breakout

New Classroom Wing Additions: (2) science labs, (4) classrooms, (1) new band breakout space, cafeteria expansion, (2) additional band breakout room renovations

Practice Gym Addition: locker rooms, coaches’ offices, other support spaces, storm shelter (12,000 SF) 

The construction of the new gym will be ICF walls and a unique steel joists roof structure.

These renovation projects are a part of the Mesquite ISD 2019 bond. Did you know we also partnered with Mesquite ISD on their 2018 Bond projects?